Duration fields

Duration fields, such as "time spent", " aggregate time spent", "time estimate", "aggregate time estimate", "time original estimate", "aggregate time original estimate":

  • Format: the one the Jira instance has set on Time tracking “Time Time tracking format”format:

  • They are calculated based on Jira setting in “Working Working hours per day” day and “Working Working days per week”week

Transitions area - duration fields

"Time in final status" and "Time in initial status":

  • Format: the one the Jira instance has set on Time tracking “Time Time display format”format

  • They are calculated in real hours, not working hours. For example:

    • 3 days = 72 real hours, even if there are only 24 working hours.